AS13030

Status Info

Ticket:#9249
Title:Planned Maintenance: Zurich, Equinix && Zurich, ICT-Center && Bern, VTL
Duration:2015-10-14 23:00 - 2015-10-15 03:00
Severity (1-5):1
Status: Done

We will conduct a software upgrade of the core router in ZRH-2, Equinix Zurich. For this work we plan a downtime of approximately 30 mins during the time from 14.10.2015 23:00 to 15.10.2015 03:00.

This will have an impact for the fallowing services:
- ZRH-2, Equinix Zurich: All services will be down
- ZRH-4, ICT-Center Zurich: All services will be down
- BRN-1, VTL Bern: Service at risk. This applies also to all Fiber7 customers in 640BRE, 640LAG, 640BUE, 640BEM, 640WEH, 640KOE, 640BOL, 640BUZ and 640WAB. 

----- 

Wegen eines Software-Updates unseres Core-Routers in ZRH-2, Equinix Zurich werden folgende Services fuer ca. 30 Minuten unterbrochen werden:

Zeitfenster: 14.10.2015 23:00 bis 15.10.2015 03:00

- ZRH-2, Equinix Zurich: Unterbruch aller services
- ZRH-4, ICT-Center Zurich: Unterbruch aller services
- BRN-1, VTL Bern: moeglicher Unterbruch (service at risk). Dies betrifft auch alle Fiber7 Kunden in 640BRE, 640LAG, 640BUE, 640BEM, 640WEH, 640KOE, 640BOL, 640BUZ and 640WAB.

Update 23:50 CEST

This maintenance has been concluded. We see all services up again.